2009.07.01 HUEBER Getriebebau invests more than one million Euro in its location in Kirn

Beginning of August 2008 the construction works on the site adjacent west to HUEBER Getriebebau GmbH have started.
On this site an approximately 850 m² production hall plus 250 m² warehouse are to be built.
Among others this major investment was possible by participation of Krupke Holding GmbH who fully supports this strategic orientation of HUEBER Getriebebau GmbH.

From beginning of 2009 the field of gearbox service and repair, especially for wind turbine gearboxes, will be established in the new facility.

The large crane capacity of totally more than 60 tons ensures that HUEBER can handle heavy-load gearboxes exceeding 50 tons/piece – gearboxes like the one delivered in December 2007 to Rohrwerk Maxhütte.

Furthermore the new workshop includes a new painting facility in which the gearboxes are painted on a high technical standard.

In the run-up to this decision for Kirn as the location for the new production hall there have been further investment possibilities that were thoroughly checked by the management. The decision to execute the extension at the company’s location in Kirn is mainly connected with logistic aspects.

By means of the building activities the appearance of HUEBER Getriebebau GmbH will be adapted to the positive developments of the last years.

The land area including the adjacent residential building already belonged to HUEBER Getriebebau GmbH. The residential building is to be converted into an office building with staff rooms and thus integrated into the new building.
 
With this extension HUEBER institutes the option of establishing new jobs at Kirn and thus further consolidating this location.

You will find press releases here (German versions):

Allgemeine Zeitung Kirn, 06.09.2008 continue…

Allgemeine Zeitung Kirn, 26.11.2008 continue...

Allgemeine Zeitung Kirn, 11.02.2009 continue...

Kirner Zeitung, 12.02.2009 continue...

Allgemeine Zeitung Kirn, 06.03.2009 continue...

Here you’ll find some impressions of the construction works:

Drawn in are the 1st (850 m² production hall) and 2nd (250 m² warehouse) phase of construction.


Before start of construction - beginning of August 2008


Land preparation for building - August 2008


Construction works - beginning of October 2008


Steel construction - November 2008


 

Steel construction - beginning of December 2008


  

Steel construction and structual fire protection - beginning of December 2008


Inside BA1 - middle of December 2008


Inside BA2 - middle of December 2008


Steel and plate construction - middle of December 2008


Inside BA1 - end of December 2008


Plate construction - end of December 2008


Insulation BA2 - beginning of January 2009


 

Insulation BA1 - beginning of January 2009


Exterior facing BA1 - middle of January 2009


Placing the bottom plate - middle of January 2009


Placing the bottom plate - middle of January 2009


Exterior facing - end of January 2009


Inside BA1 - beginning of February 2009


Inside BA1 - beginning of February 2009


Crane runway - beginning of February 2009 


Exterior facing BA1 - beginning of February 2009 


Delivery of the crane girders - middle of February 2009


Installation of the crane girders - middle of February 2009


Fitting of the trolley - middle of February 2009


 

New spray booth - beginning of March 2009


View into the new spray booth - beginning of March 2009


Access to the former residential house - beginning of April 2009


Exterior facing BA1 - April 2009 


New porch roof at the new cleaning area - June 2009 


Exterior facing BA1 - July 2009 


Completion of the exterior installations - July 2009 